A delivery recovery plan should identify the quantity needed by each usable-material date, establish what the supplier can actually deliver, and assign the decisions needed to close the gap. “Expedite the order” is a request. A recovery plan says which lot moves, by which route, at whose approved cost, and what happens if the next milestone slips.
Use the blank delivery recovery plan (Excel) during the supplier call, then complete the decision and milestone sections with planning and logistics.
Establish the actual shortage
Start with the affected PO lines, latest approved requirements, original supplier commitment, and revised proposal. Preserve the previous dates so the team can see what changed.
Ask planning for usable inventory and dated demand. Separate available stock from material already allocated, blocked in quality, or awaiting transfer. Record the minimum quantity needed to keep the next operation running. The full order quantity and the immediate shortage are often different.
Define three dates explicitly: supplier dispatch, receipt at the destination, and availability for use after required receiving or inspection steps. Microsoft’s planning documentation distinguishes requested ship and receipt dates and describes how transport and calendars affect its calculations. Your recovery plan needs the same clarity, whatever system holds it. Microsoft date documentation.
The result should be a statement such as: “We need 180 accepted units available to production by Tuesday morning; the next 420 are required Friday.” That is actionable in a way “600 units are late” is not.
Find the constraint before choosing the remedy
Ask what prevents the supplier from meeting the date. Material shortage, unfinished production, inspection, missing paperwork, and a missed carrier pickup need different interventions.
Request facts that test the proposed recovery:
- Quantity finished, quantity inspected, and quantity released to ship.
- Earliest remaining production and inspection completion times.
- Packaging and document readiness.
- Dispatch location and carrier booking cutoff.
- Earliest feasible split quantities and arrival dates.
- Named supplier owner for each unresolved constraint.
Do not pay for faster transport before establishing when goods can be released. A same-day freight quote cannot recover three days of unfinished production.
Build options with a common comparison basis
For each option, capture usable quantity by need date, evidence supporting it, incremental cost, approvals, and the last time the team can act. Options might include a partial shipment, a different transport service, an internal stock transfer, or a planning change.
An alternative supplier or substitute specification needs the buyer’s and relevant technical owner’s review. Record qualification, testing, tooling, and release dependencies before calling it available supply.
Check who arranges and pays for any transport change against the agreed terms. Incoterms address responsibilities, costs, and risks, but the specific rule and named place matter. The International Trade Administration provides a useful Incoterms overview. Escalate unclear responsibility rather than assuming a supplier owes every expedite cost.
Keep an estimated avoided disruption separate from an actual saving. Use planning’s stated consequences and assumptions; do not manufacture a line-stop value to make one option look attractive.
Worked example: recover the first need, then the balance
In this illustrative example, 600 housings were due Monday. The supplier reports that 200 can pass inspection Monday afternoon and 400 will be ready Thursday. Planning has enough usable inventory through Tuesday and needs 180 additional units Wednesday morning.
The buyer and logistics team compare three paths. Standard transport brings the first lot Thursday, too late. An express service can deliver the 200 Tuesday afternoon for an additional $480. An internal transfer can provide 100 Tuesday, but leaves another 80 needed Wednesday.
The chosen proposal is express transport for the first 200 and standard transport for the remaining 400, subject to the authorized cost approval and supplier release confirmation. Receiving confirms it can inspect the first lot Tuesday afternoon. Logistics confirms the remaining 400 can arrive the following Tuesday, with receiving able to inspect them that afternoon. Planning needs no further housings before the following Wednesday, when it needs 400. Both lots therefore have a proposed usable date before their respective production requirements.
The plan includes a Monday 2 p.m. release checkpoint. If inspection is incomplete then, logistics may miss the carrier cutoff. The fallback decision goes to the planning owner at that time, while options still exist. Nobody marks the issue resolved merely because express freight was quoted.
Assign milestones that prove progress
Use events that change confidence in the outcome: production complete, inspection released, carrier booked, goods collected, arrival confirmed, and receipt accepted. A supplier’s “on track” message is helpful context but does not replace the evidence required at a critical checkpoint.
For each milestone, record the due time with a time zone, responsible person, evidence expected, and escalation action if missed. Replace superseded dates without deleting the history. Keep approved costs and quantities aligned with the current plan.
Systems can support downstream-impact review: Microsoft documents a workspace for reviewing changes to confirmed POs and their effect on demand. Check your own system’s configuration and coverage, then add any dependencies it does not capture. Microsoft changed-order documentation.
Calculate coverage by the time material becomes usable
Build a small dated balance with planning. Start with usable stock after existing allocations. Add receipts only on the date the responsible team expects them to become usable. Subtract demand in the order it occurs. Keep unapproved substitutes and blocked inventory outside usable supply.
Extend the illustrative housings example. At Monday’s close, planning has 240 usable housings. Demand is 240 Tuesday, 180 Wednesday, and then 400 the following Wednesday. The first 200 recovered housings become usable Tuesday afternoon, before Wednesday’s production. The final 400 become usable the following Tuesday afternoon, before the next requirement.
Monday closing balance: 240
Tuesday: 240 - 240 + 200 = 200
Wednesday: 200 - 180 = 20
No further demand before next Wednesday: 20
Following Tuesday: 20 + 400 = 420
Following Wednesday: 420 - 400 = 20
If the first 200 are only usable Thursday, Wednesday’s balance becomes zero minus 180, a shortage of 180. An arrival message Tuesday is therefore insufficient if receiving cannot inspect until Thursday. Confirm that inspection capacity and required documentation support the assumed usable date.
The balances are illustrative and assume no other allocations, rejects, or demand changes. Record the planning snapshot time and refresh the calculation when any of those assumptions changes. A recovery that worked yesterday can stop working after production pulls demand forward.
Set a fallback before the carrier cutoff
For each critical milestone, state what fact triggers the fallback and who can authorize it. Avoid conditional plans such as “air freight if needed” with no booking cutoff, goods-ready confirmation, or budget owner.
In the example, logistics needs a release confirmation by Monday 2 p.m. At 1:30 p.m. the buyer checks with the supplier. If release is uncertain, the buyer prepares the known alternatives and asks planning for a decision before the slot expires. Preparing an option does not authorize spending or changing production.
If the shipment is collected but delayed in transit, switch the checkpoint to carrier evidence and the next feasible arrival. Do not continue chasing the supplier’s production team for a step already completed. If the same recovery option fails twice, refresh the underlying constraints instead of simply moving the promised date again.
Handle damaged, incomplete, or undocumented arrivals
A truck arrival can contain less usable supply than expected. Receiving records the actual count and condition. Quality decides the acceptance or release disposition. Procurement obtains missing documents and replacement proposals; it does not override either function’s record.
If 200 arrive but only 170 are released, rerun the balance using 170. Track the other 30 under their actual status, with a quality owner and next decision. Follow the partial shipment guide for quantity reconciliation and the missing certificate guide when documentation blocks review.
Where the supplier offers a credit instead of replacement material, ask planning whether the operational shortage remains. A commercial credit can resolve a financial issue while production still lacks the part. Keep those outcomes separate and route the financial work to its owner.
For a proposed cancellation, verify what is already made, released, or in transit, and obtain the authorized commercial decision. Do not assume that cancelling a system balance stops a supplier shipment already underway.
Measure recovery against a fixed requirement
Choose the cohort and outcome before reporting. One useful measure is affected requirement events supplied with the required usable quantity by the approved need time, divided by all requirement events covered by recovery plans in the period. A requirement event is a defined item, site, quantity, and time; explain how split events are counted.
Keep original and subsequently revised need times visible. Report results against the original requirement alongside any approved replanning outcome, so moving production does not make a missed commitment disappear. Identify whether a miss arose in production, transport, receiving, documentation, or internal decision waiting.
Track actual incremental recovery spend separately from estimated avoided disruption. For ten recovered requirement events, eight met on time means 80% for that cohort. It does not prove that eight production stoppages were prevented. Record confirmed costs and evidence of operational coverage; label counterfactual loss estimates as assumptions.
Close on the operational result
Close the recovery when the agreed quantities are received and available as required, residual shortages have explicit dispositions, and the order record reflects the actual outcome. Keep any freight dispute or supplier credit request separately open until its own evidence supports closure.
If the initial problem is still an unclear supplier commitment, use the unconfirmed PO playbook first. Mandel’s purchase order management work helps carry the follow-up and authorized updates through this sequence, while people retain decisions about supply, specifications, and commercial tradeoffs.

